Page Title: RECHECK VERTICAL AND HORIZONTAL RUNOUT OF POWER TURBINE SHAFT
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

TM 9-2835-255-34
LOW PRESSURE TURBINE NOZZLE REPLACEMENT (Sheet 8 of 11)
8.  RECHECK VERTICAL AND HORIZONTAL RUN-
OUT OF POWER TURBINE SHAFT (1).
a.
Move dial indicator assembly (2) to 12 o'clock
position and reset indicator gauge pointer to
zero.
NOTE
In the following step, observe and record
dial readings obtained at noted clock
positions.
b.
Rotate power turbine shaft (1) to 3 o'clock
position, to 6 o'clock position, to 9 o'clock
position and back to 12 o'clock position.
c.
If dial reading is between 0-0.005 inch (0-
0.127 mm) at any two opposing clock posi-
tions, go to step (9).
d.
If dial reading is greater than 0.005 inch (0.127
mm) at any two opposing clock positions, re-
peat steps 6 through 8.c.
9.  REMOVE DIAL INDICATOR ASSEMBLY (2) FROM
POWER TURBINE SHAFT (1).
CAUTION
Do not remove G.P. turbine runouts fixture
(3) or unload power turbine shaft by re-
moving plug from forward end of power
turbine shaft (1) (Ref. step 4.). Damage to
parts may result.
Go on to Sheet 9
6-99