TM 9-4910-736-14&P
(2)
Set FUNCTION switch to COND.
Set CONDENSER switch to LEAK.
(3)
WARNING
When PUSH TO TEST switch is depressed, HIGH VOLTAGE is
present across TEST LEADS and condenser under test. DO NOT
touch leads or condenser under test when PUSH TO TEST
switch is depressed.
(4)
Observe WARNING and depress PUSH TO TEST switch. Meter reading
should be within the green LEAKAGE bar at the left of the dial.
Release the PRESS TO TEST switch.
(5)
(6)
Set FUNCTION switch to OFF.
Disconnect test leads from condenser.
(7)
c.
Series Resistance Test.
Proceed as follows:
(1)
Set FUNCTION switch to COND.
(2)
Set CONDENSER switch to SERIES RES.
Connect TEST LEADS together.
(3)
(4)
Using ZERO ADJ OHM AND SERIES RES control, adjust meter reading
to SET LINE.
Connect TEST LEAD with red boot to pigtail of condenser and the
(5)
other TEST LEAD to condenser case. Meter reading should be within
the green SERIES RES bar at the right of the dial.
(6)
Set FUNCTION switch to OFF.
Disconnect TEST LEADS from condenser.
(7)
d.
Capacitance Test.
Proceed as follows:
(1) Set FUNCTION switch to COND.
(2) Set CONDENSER switch to CAP.
(3) Connect TEST LEAD with red boot to pigtail of condenser and the
other TEST LEAD to the condenser case. Meter reading of capacitance
on the red scale should be within rated tolerance.
initial procedures, coil primary resistance, coil primary-to-case resistance,
coil secondary resistance, and coil secondary-to-case resistance. (See figure
2-3.)
|