43. USING HOISTS AND LIFTING SLING (1), RAISE
FORWARD ENGINE MODULE (2) FROM WOOD
BLOCKS (3,4) ON FLOOR.
a.
Attach chain fall hoist hook (5) to shackle (6)
and take up slack.
b.
Attach hook (7) of lifting sling (1) to pin (9) and
take up slack.
c.
Slowly raise aft end (8) from wood block (3),
but not from wood block (4), while simulta-
neously lowering forward end (10).
d.
Continue raising aft end (8) until forward en-
gine module (2) is tilted enough to allow re-
placing hoist hook (5) with sling hook (11) at
shackle (6).
e.
Remove hoist hook (5 ) from shackle (6) and
connect sling hook (11) to shackle (6).
f.
Raise forward engine module (2) to horizontal
position.
44. INSTALL FORWARD MODULE (PAGE 5-13).