p. Secure the left-hand side of shelf support beam (1)
by sliding out end and inserting into vertical shelf
1
2
support "E-track" (2). Lower end of support beam
until lever (3) is completely engaged.
q. Repeat Step m on the right-hand side of shelf
support beam (1).
r. Repeat Steps i through n until all four shelf
support beams (1) have been adjusted to the same
height.
s. Install shelves (1) on top of support beams (2).
1
2
After the shelf support beams have been adjusted to
desired positions (refer to Paragraph 2.8) the container
may be loaded.
a. For easier loading, it is usually desirable to place
heavier items on the floor or lower shelves.
Distribute the load as evenly as possible.
b. To prevent excessive movement, fill each shelf as
much as possible.
c. Tie-downs are provided in all corners and along the
tops and bottoms of the side and front walls. Cargo
may be secured to these tie-downs using rope or
webbing.
2-6.2 Change e 1