2-12. Storage procedures. In the event the Electric/
Instrument Shop is to be placed in storage the provisions
of TM 740-90-1, TM 743-200-1 and applicable shop
equipment TM's will be followed.
2-13. Striking the shelter. Procedures for striking the
shelter are contained in TM 10-5411-201-14.
In
addition, the following "Supplemental Instructions" will be
observed.
a.
Remove screws (1) at both corners of fold-out
floor.
b. Install cable (3) and retainer block (2) with
screws (1).
NOTE
When floor is lowered, (to allow roof clearance for folding) the devices securing
fold-out floor counter-balance cables can be disengaged.