TM 55-4920-439-13&P
2. As soon as there is enough floor area (4),
the personnel inside will move to the expanded side of
the shelter raising the roof with extended support struts
(2).
3. Once the struts (2) are totally supporting the
roof panel (1), the end walls (5) are swung open.
WARNING
The fold-out floor counterbalance cables must be secured in the cable housings
prior to raising the shelter floor from its lowered position to its level position. If
the counterbalance cables are not secured, the counterbalance cables will remain
under tension. DO NOT attempt to remove cables if the counterbalance cables are
not secured. Removing cables while under tension could cause serious injury to
personnel.
4. (For shelter P/N 136-0000-101) Raise the
upper lockout plates (6) on each end wall and install
upper lockout pins (7) into the cable housings.