c. Two people inside the shelter, using the support
struts (1), will lower the roof panel (2) until two personnel
outside can reach and hold the weight of the roof.
d. Inside personnel will shorten the struts (1) and
secure to roof brackets (3). They will then move into
position to assist outside personnel.
e. After all inside personnel are clear, allow the
roof panel (2) to close to the vertical position.
f. After shelter has been folded as detailed in steps a thru e and prepared in accordance with TM 10-5411-201-14,
the Propeller/Rotor Shop is ready for transport or storage.
Change 1 2-33/(2-34 blank)
|