TM 55-4920-411-13&P
SERVICE UPON RECEIPT
Section 1. SITE AND SHELTER REQUIREMENTS
2-1. Siting.
The only requirement for operating the Temperature
and Speed Simulator is the availability of 115 vac, 50-
400 Hz power source supplying 10 volt-amperes.
Section Il. SERVICE UPON RECEIPT OF MATERIEL
2-2. Unpacking.
a. Packaging Data. When received, the Temperature
To open the test set, release air pressure
and Speed Simulator is packaged In a corrugated
by opening the air release valve.
cardboard carton 50.8 cm (20 inches) long by 50.16
cm (19-3/4 inches) wide by 41.275 cm (16-1/4 inches)
a. Inspect equipment for damage caused during
shipment. If equipment has been damaged, report it on
deep. The volume of the carton is 0.1 cubic meters (3.7
DD Form 6 in accordance with instructions in AR
cubic feet), and the total weight of the carton when
700-58.
packed for shipment is about 14.4 kg (32 pounds). A
typical shipping carton and contents is shown in Figure
b. Check equipment against component listing in
2.1.
operator's manual anti packing slip, to see if shipment is
complete. Report all discrepancies per instructions of
b. Removing Contents.
DA PAM 738-751. Equipment should be placed in ser-
(1) Cut or remove gummed tape from top of
vice even though a minor assembly or part that does not
carton, and open top of carton
affect proper functioning is missing.
c. Check to see whether equipment has been modi-
(2) Remove polyethylene cushioning material
fied (Equipment which has been modified will have
from top of carton.
the MWO number on the front panel, near the no-
(3) Lift carrying case from carton and remove
menclature plate.) Check also to see whether all cur-
remaining polyethylene cushioning material.
rently applicable MWO have been applied. (Current
MWO applicable to the equipment are listed in DA PAM
310-1.)
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |