TM 9-6920-737-10
SYSTEM (LONG-TERM) POWER-DOWN PROCEDURE (Continued)
4.
At emergency light (4) set toggle switch (5) to OFF position and observe emergency lights go out.
5.
In Trainer Shelter at emergency light (6) set toggle switch (5) to OFF position and observe emergency lights go
out.
6.
Open Integration Shelter door.
NOTE
Integration Shelter Air Conditioner and lighting will go off and emergency light will light when step 7 is performed.
7.
Open Utility Power Distribution Panel door (7) and set the four circuit breakers (8) to OFF position.
8.
Set main circuit breaker (9) to OFF position and close panel door.
WARNING
Use caution when leaving the shelter to avoid personal injury. All shelter lighting will be off after step 9 is performed.
9.
Locate emergency light (10) and set toggle switch (5) to OFF position.
10.
Leave Integration Shelter and lock the door.
11.
Make sure remaining shelter doors are locked.
12.
Make sure that organizational maintenance is notified that the U-COFT System is completely powered-down.
Change 1 2-208
|