TM 94910-736-14&P
a. Initial Procedures. Proceed as follows:
(1) Turn FUNCTION switch to OFF.
(2) Connect BAT LEADS to battery as follows: Red +12 V lead to
+ terminal and black -12 V lead to - terminal.
(3) Set FUNCTION switch to OHM.
(4) If test is being performed on a coil mounted in the vehicle,
disconnect the primary leads from + and - coil terminals and
disconnect secondary lead from coil tower. (If the coil is
Delco-Remy 1115282, disconnect connectors marked "-" and
SECONDARY and remove the lead attached with screw in the center
of the coil.)
b.
Coil Primary Resistance Test. Proceed as follows:
(1) Set OHMMETER RANGE switch to 0-15.
(2) Connect TEST LEADS together, and using the ZERO ADJ OHM AND SERIES
RES control, adjust meter reading to zero ohms.
(3) Connect TEST LEADS to + and - coil terminals. (If the coil is
Delco-Remy 1115282, connect one TEST LEAD to the pin inside the
connector marked "-" and the other TEST LEAD to the center screw on
the opposite side of the connectors.) Typical coil primary
resistance readings are as follows:
Manufacturer part no.
Coil primary resistance
Autolite - Prestolite 115049
P&D Mfg. VC2 X
1.5 ohms
Delco-Remy 1915992
7 ohms
Delco-Remy 1115282
c. Coil Primary-To-Case Resistance.
Proceed as follows:
(1) Set OHMMETER RANGE switch to 0-100K.
(2) Connect TEST LEADS together, and using the ZERO ADJ OHM AND SERIES RES
control, adjust meter reading to zero ohms.
(3) Connect one TEST LEAD to coil case and the other LEAD to one
primary terminal. The reading should typically indicate an open
circuit.
d.
Coil Secondary Resistance. Proceed as follows:
(1) Set OHMMETER RANGE switch to 0-100K.
(2) Connect TEST LEADS together, and using the ZERO ADJ OHM AND SERIES RES
control, adjust meter reading to zero ohms.
2-8
|