|
|
TM 750-245-4
piece shall be determined from the difference of the two
b. Generally, magnesium castings which have
measurements.
been formerly sandblasted, are pickled or treated with a
sulfuric or nitric-acid solution.
Treatment should
c. Other Tests. Treated pieces shall be tested for
continue until 0.002-inch surface is removed, if
conformance with any special requirements specified in
dimensional requirements permit.
the drawing. The tests shall be performed according to
the methods specified therein.
c. Old paint coatings are usually removed by use
of (caustic) liquid paint remover. This operation should
d. Rejection.
be followed by a wash or rinse to thoroughly remove and
(1) In the event unsatisfactory quality is
neutralize the alkaline.
detected in the processing treatment being used, the
d. Insure proper treatment is used as required.
inspector will promptly notify processing personnel to
The following can be used for magnesium treatments:
take necessary corrective action. All work which was
processed under doubtful conditions of the solution
(1) Chrome pickle treatment.
utilized will be rejected and reprocessed to the
(2) Dichromate treatment.
satisfaction of the inspector.
(3) Galvanic anodizing treatment.
(2) If a sample fails to conform to the
(4) Chromic acid brush-on treatment.
requirements of this document, all items being
(5) Fluoride anodizing process plus corrosion
processed as represented by the sample will be
preventive treatment.
rejected.
Rejected items may be submitted for
(6) Chromate treatment.
acceptance after the items have been reprocessed.
Reprocessed items are subject to 100 percent
e. Random sampling for visual examination and
inspection in order to determine if defects still remain.
workmanship shall be conducted.
2-15. Magnesium-Final Inspection
f. All items exposed, to weather shall be examined
a. All equipment fabricated of magnesium will be
very closely for any evidence of corrosion or
inspected for the proper smoothness and finish.
deterioration of finish. If there is any evidence of
corrosion, the finish must be removed to bare metal and
b. Any detected bare spots will be refinished as
cleaned of any corrosion or corrosion products and
required.
finished using procedures provided.
2-14. In-Process Inspection
dirt, grease, and pits will be removed and any necessary
a. Product Examination. Samples of treated parts
actions required will be taken to correct the problem.
shall be visually examined to determine conformance to
d. Check those areas that specify special painting,
workmanship standards, quality of the treated surface,
etc.
and any other requirements specified by the system
e. Scratches which must be removed and
documentation. A visual examination of the processed
reworked and / or finished.
surface shall be made for complete and uniform
f. Coatings shall be visually examined for
coverage. Surfaces shall be examined for coloring and
continuity and uniformity.
general characteristics, described herein, particular to
g. Coatings shall be checked for dry film thickness
the type treatment being examined, which shall be an
as required by this document and / or the applicable
indication of satisfactory time of treatment and condition
system documentation. Small steel panels prepared
of solution.
with films should be used as comparators to the item
b. Dimension Change Determination.
The
being inspected.
thickness of each piece selected prior to treatment shall
h. The thickness requirement generally shall be
be determined by measuring with a micrometer which
considered met when the coating is of sufficient
reads accurately to 0.0001 inch. The pieces shall then
thickness to completely cover and impart characteristic
be processed concurrently with the remainder of the lot.
color of the coating to the surface. Generally, four mils
The pieces shall be distributed throughout the various
thickness is sufficient if a surface is completely stripped;
bitches during processing so as to be representative of
otherwise, a five mil thickness is acceptable and
the entire lot. The thickness of each piece shall be
adequate.
determined after treatment by measuring the same
location as before. The dimensional changes of each
2-4
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |