TM 55-4920-439-13&P
2. From storage
chest
remove
a
quick
disconnect coupling (4).
3. Install the quick disconnect coupling (4) on
air inlet nipple (2).
4.
Tighten coupling (4) securely.
b.
Water supply connection.
NOTE
When water is to be supplied to shelter proceed as follows.
1. Remove protective dust cap (1) from each
end of water feed thru connector (2).
2.
Install adapters and fittings as required.
NOTE
Reposition storage chest in mounting bracket when no longer required.
2-7. Checking shelter level. Once all equipment is in the recommended operational position recheck leveling of shelter.
Use procedures in TM 10-5411-201-14 to verify and adjust level. Correct adjustment is essential to ensure proper
operation of machine tools, doors and access panels.
The Electric/Instrument Shop is now operational.