2-1. Setup of Propeller/Rotor Shop upon initial receipt. Refer to TM 10-5411-201-14 for specific procedures
concerning erection of the tactical, one side expandable, shelter (NSN 5411-01-124-1377).
a. The Propeller/Rotor Shop should be set up with power cable length, tactical deployment, exhaust/Inlet of ECUs
and phasing between related shops kept in mind. The shop's power entry panel, next to the personnel entrance door,
should be facing toward the power source and power distribution panel (see page 1-0).
b. Initial Leveling.
Procedures in TM 10-5411-201-14 will be followed to ensure proper operation of all fold-out
panels.
WARNING
When all equipment and materiel is stored on the stationary side of the shelter, the
limited floor space presents a safety hazard to operating personnel. This is most
critical during the raising and lowering of the roof panel. Failure to observe
supplemental instructions could result in serious injury to personnel. Personnel
inside the shelter could become trapped between the roof panel and equipment
bolted to the floor.
c. Supplemental Safety Instructions. To prevent possible accidents, the following procedures will be followed:
1. Two personnel, outside the shelter, must lift
the roof panel (1) far enough to allow two people inside
to release the support struts (2), extend them to full
length, and insert the quick-release pins (3).