TM 55-4920-433-13&P
2-7. Checking shelter level. Once all equipment is in the recommended operational position recheck leveling of
shelter. Use procedures in TM 10-5411-201-14 to verify and adjust level. Correct adjustment is essential to ensure
proper operation of machine tools, doors and access panels.
The Pneudraulic Shop is now operational.
SECTION III. PREPARATION FOR SHIPMENT
2-8. Striking the shelter. Shop utilities (other than electrical).
a. Disconnecting water supply. (When installed)
1. Obtain two protective dust caps (1) from
shop storage chest.
2. Install dust cap on each end of feed thru
connector (2), tighten securely.
b. Disconnecting compressed air.
1. Remove quick disconnect coupling (1)
from the air inlet nipple (2). Store in shop storage chest.
2. Obtain a dust cap (3) from storage chest.
3. Install dust cap (3) on air inlet nipple (2),
tighten securely.
2-19