Click here to make tpub.com your Home Page

Page Title: Figure 5-1. Blocking and tiedown of the RTCC superstructure on the M747 semitrailer (sheet 4 of 7).
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

TM 55-3810-306-15
(continued)
NOTES:
3. Suspension and fifth wheel loads shown are
1. Loading sequence: Install the track layering and
from  actual  weighing  of  loaded  RTCC
crossbeams where indicated. Crossbeams are
superstructure
on
MS52162
semitrailer.
bolted through layering and metal tracks. Spike
Weights may vary slightly because of variations
unbolted crossbeams to the track layering (see
in blocking materials and components.
note 7 below).  Spike the slide plates to the
turntable crossbeams (see view E-E, sheet 7) as
shown.  Build and bolt the laminated block
4. Cushion and secure floodlights, wipers, mirrors,
assembly to the bottom surface of the turntable
and fans with tape.
bearing.  Locate the holes in the laminated
block by means of a cardboard template made
5. See  superstructure  demount
procedure
in
from the hole spacing in the bearing.  Bolts,
appendix A for disassembly.
nuts, and washers that were removed during the
demount of the superstructure may be used for
6. Each tiedown shown is a single length of .62-
bolting the superstructure to the laminated block
inch diameter wire rope looped through a trailer
assembly.  Lower the superstructure onto the
pocket or ring and crane lug. Ends are joined as
semitrailer so that the laminated blocking
shown in detail A. Tension all ropes to 3,000
contacts the slide plates.  Position the load
pounds and torque rope clamp nuts to 95-foot-
longitudinally as shown, and center it laterally.
pounds.
Support the boom so that the top surface of the
boos is level with the trailer. Build and install
the counterweight and boom support structures
7. Wood joints in structures, planking, beams, and
as shown to fit the leveled load.  Install the
supports, where bolting is not specified, shall be
tiedowns as shown (see note 6 below).
assembled using nails as follows: Nail through
turntable block laminations using sixteen 20d
nails.  Nail slide plate members through into
2. RT875CC  superstructure  load  consists  of
crossbeams using 20d nails. Where toenailing
components shown, including superstructure,
is required to assemble 4 by 4, 4 by 6, 4 by 8,
44,191 pounds; main hook block, 758.5 pounds:
and 6 by 8 beams, stakes, blocks, or to join
and overhaul ball, 229 pounds.  This equals
beams or blocks or stakes to planking or
45,178.5 pounds plus blocking and tiedowns.
crossbeams, use 30d nails and predrill top
member of joint to .156-inch diameter.
Figure 5-1. Continued (sheet 4 of 7).
5-6