TM 55-1915-200-10
2-5.31.3. Sequence of Lifting Operation.
c. Plug power cord (8) into davit boom socket (7)
and into shipboard 115 volt AC electrical outlet located
WARNING
in starboard stairwell leading to starboard aft mooring
station.
Never use davit and winch for any type of
human support or transportation.
d. Turn switch on electric remote control to the
OUT position to release tension on cable and lifting
Operator should never lift a load over
hook (17, FIGURE 2-200, Sheet 2 of 2).
assistants or other personnel.  No one
should walk under a hoisted load. Severe
e. Remove lifting hook (17) from lifting hook
injury or death could result should winch or
keeper (16).
davit  equipment  fail.
Operator  is
f. Remove boom support pin (10, Sheet 1 of 2)
responsible for ensuring load is safely
from boom support pin recess (4) by loosening
attached. Operator MUST NOT attempt to
thumbscrew (5) and turning boom support pin (10)
hoist  loads  until  absolutely  certain
clockwise to disengage retainer tab (11).
conditions of load and winch will allow safe
operation.
WARNING
CAUTION
Exercise care to prevent davit from swinging to
one side during lifting procedure.
Always stop winch before load reaches
davit boom. Never unwind all cable from
drum when paying out.  Always leave at
g. Using three soldiers, manually raise davit boom
least five wraps of cable on drum.
to 45 degree angle, exposing hole (4) in boom support.
Always ensure that load has come to a
h. Secure davit in upright position by inserting and
complete stop and is stable prior to
locking boom support pin (10) into hole (9) in boom
changing direction of winch.
support.
Lock  boom  support  pin  by  turning
counterclockwise to engage slot in retainer tab (11).
Turn thumbscrew (6) clockwise.
a. Lift load by turning control switch (12) to the IN
position. Winch will continue to hoist load as long as
2-5.31.2. Lifting Operations. Perform the following tasks.
operator holds switch to the IN position. Winch will stop
hoisting load when operator releases switch.
a. Attach hook to load.
b. Push boom around the swivel base until load is
b. Raise load enough to clear handrails.
over the unloading point.
c. Pivot boom to desired lift position.
c. Lower load by turning switch (12) to the OUT
position. Load will continue to lower until operator
2-531