TM 55-1905-223-24-4
e. Remove chocks from resilient mounted components.
2-5. Installation Instructions.
WARNING
DO NOT lift the generator set using only the engine or generator lifting eyes.
NOTE
The approximate weight of the generator set is 1514 lbs (687 Kg).
a. Position the generator set for good service accessibility on all sides.
b. Lift the generator set into position by sliding two lifting bars into the base rail holes and connecting them to a
spreader bar.
c. The generator is skid mounted and should be bolted to the deck. The engine comes equipped with resilient
mounts.
d. When the generator set is properly mounted in position proceed as follows:
(1) Connect the exhaust outlet connection.
(2) Connect the fuel inlet connection.
(3) Connect the battery cable to the starter motor.
2-6. Preliminary Servicing and Adjustment. It is important that careful preparation be made before a diesel
engine/generator set is started-after long idle periods. It must be ready for immediate use in the event of loss of normal
service. Check all pipe connections to ensure that all systems are correctly connected.
a. Procedural steps to be taken to prepare the generator for starting are:
(1) Be sure the radiator has been filled with 50% mixture of water and antifreeze.
2-7. Initial Setup Procedure. Includes operational checks and inspections that are not performed for a routine startup.
Direct support maintenance personnel will perform initial setup in accordance with the operator's manual, TM 55-1905-
223-10.
Change 1
2-2
|