TM 55-315
c. Quality assurance records shall be identifiable and retrievable.
d. Measures shall be established to control the issuance of documents, such as instructions, procedures, and
drawings, including changes, that prescribe all activities affecting quality.
(1) Activities affecting quality shall be prescribed by documentation of a type appropriate to the circumstances
and shall be accomplished according to these procedures, instructions, or drawings. This documentation shall include
appropriate qualitative or quantitative acceptance criteria for determining that important activities have been satisfactorily
accomplished.
(2) Document control measures shall assure that documents, including changes, are reviewed for adequacy and
approved for release by authorized personnel. Changes to documents shall be reviewed and approved by the same
organization(s) that performed the original review and approval.
(3) Document control measures shall assure that documents are distributed and used where the prescribed
activity is performed.
9-9. Inspections and Tests
a. A program for inspection of activities affecting quality shall be established and executed by or for the organization
performing the activity.
(1) The inspection shall be performed by person(s) who did not perform the activities being inspected.
(2) Examination, measurements, or tests of material or products shall be performed for each work operation,
where necessary, to assure quality.
(3) If inspection of processed material or products is impossible or impractical, indirect control by monitoring
processing methods, equipment, and personnel shall be provided.
(4) If required to assure adequate quality, both measurement/tests of products and process monitoring shall be
provided.
(5) If mandatory inspection hold points (points beyond which work should not proceed until previous work has
been inspected and approved) are required, they shall be indicated in appropriate documents.
b. A test program shall be established to assure that the packaging/components perform satisfactorily.
(1) Written test procedures will include requirements and acceptance limits contained in applicable packaging
approvals.
(2) Procedures shall contain provisions for assuring that all prerequisites for the given test have been met.
(3) Procedures shall contain provisions to assure that adequate test instrumentation is available and is used and
that the test is performed under suitable environmental conditions.
c. Control measures shall be established to assure that tools, gauges, instruments, and other measuring and testing
devices used in activities affecting quality are properly controlled, calibrated, and adjusted at specified items, to maintain
accuracy within necessary limits.
d. Measures shall be established to indicate, by use of markings such as stamps, tags, labels, routing cards, or other
suitable means:
(1) The status of inspections and tests performed on separate items of the packaging.
(2) The operating status of components of the packaging, such as tagging valves and switches, to prevent
inadvertent operation.
e. Measures shall be established to assure that conditions adverse to quality such as deficiencies, deviations,
,
defective material and equipment, and nonconformances, are promptly identified and corrected.
(1) In cases of significant condition(s) adverse to quality, the measures shall assure that the cause of the
condition is determined and that corrective action is taken to prevent repetition.
(2) The identification, cause, and corrective actions taken regarding significant condition(s) adverse to quality
shall be documented and reported to appropriate levels of management.
(3) Nonconforming items shall be reviewed and accepted, rejected, repaired, or reworked according to
documented procedures.  Control measures must ensure that nonconforming items are not inadvertently used or
installed.
9-10. Special Processes, Handling, Storage, and Shipping
a. Measures shall be established to assure that special processes, including welding, heat treating, and
nondestructive testing, are controlled and accomplished by qualified personnel using qualified procedures according to all
package requirements.
b. Handling, storage, shipping, cleaning, and preservation of materials and equipment to be used in packaging shall
be controlled to prevent damage or deterioration. When necessary, special protective environments shall be specified
and provided.
9-11. Quality Assurance Audits
A comprehensive system of planned and periodic audits shall be carried out to verify compliance with all aspects of the
program and to determine the effectiveness of the program.
9-3